AS9102 defines the minimum documentation and physical verification requirements for First Article Inspection in aerospace and defense supply chains.
FAI is required on new part numbers, after design changes, after manufacturing process changes, and after a lapse in production exceeding two years.
A compliant FAI package includes three forms: Part Number Accountability (Form 1), Product Design Documentation (Form 2), and Characteristic Accountability (Form 3).
Balloon drawings are a critical FAI deliverable — every inspected dimension must be cross-referenced to the inspection data sheet.
An incomplete or undocumented FAI is a major nonconformance under AS9100 and can trigger a supplier corrective action request (SCAR).
What Is AS9102 and Why Does It Exist?
The standard was developed in response to persistent quality escapes in aerospace supply chains where parts passed incoming inspection but failed in service because critical characteristics were never systematically verified on the first production article. AS9102 creates a common language between OEMs, Tier 1s, and their suppliers so that ‘we did a first article’ actually means something verifiable and auditable. It is referenced directly in AS9100 Rev D clause 8.1.3, which means any AS9100-certified organization must have a process for FAI that aligns with its requirements. For procurement professionals, requiring AS9102-compliant FAI packages from your supply chain is not bureaucratic overhead — it is one of the most cost-effective risk controls available.
When Is a First Article Inspection Required?
The five primary FAI trigger conditions are:
- New part number — any part entering production for the first time.
- Design change — any revision to the engineering drawing or model that affects form, fit, or function.
- Manufacturing process change — a change to tooling, equipment, facility, or process sequence that could affect part characteristics.
- Production lapse — parts not produced for two or more years require a new FAI to verify process capability has not degraded.
- Natural disaster or facility move — any event that could disrupt the established manufacturing environment.
A common procurement mistake is assuming a previously qualified supplier does not need a new FAI after a quiet engineering change order. Even a tolerance tightening on a single dimension constitutes a design change and requires at minimum a partial FAI covering the affected characteristics. Always include FAI requirements explicitly in your purchase order terms.
The Three AS9102 Forms Explained
Form 1 — Part Number Accountability: This form documents the top-level part being inspected, all sub-assemblies, and every raw material and purchased part that goes into it. Material certifications (certs of conformance, material test reports) are attached here. The goal is to prove that every input into the part is documented and traceable.
Form 2 — Product Design Documentation: Form 2 accounts for every design document that governs the part — the drawing revision level, any applicable specifications (AMS, MIL-SPEC, ASTM), process specifications, and surface finish requirements. This form confirms the supplier is working from the correct, current revision of all applicable documentation. A common audit finding is Form 2 referencing an obsolete drawing revision.
Form 3 — Characteristic Accountability: This is the measurement data form. Every characteristic called out on the drawing — dimensions, tolerances, GD&T callouts, surface finish values — is listed, measured on the first article, and compared to the engineering requirement. Actual measured values must be recorded. Pass/fail stamps alone are not acceptable under AS9102B. This form is where balloon numbers from the drawing directly map to inspection results.
Balloon Drawings and Characteristic Identification
Proper ballooning requires identifying all of the following: linear dimensions with tolerances, geometric dimensioning and tolerancing (GD&T) feature control frames, surface finish callouts, material callouts, weld symbols, coating or treatment requirements, and any notes with inspectable content. This is more than just dimensioned geometry — a drawing note that says ‘all edges break 0.005 inch to 0.015 inch’ is a characteristic and must be ballooned and measured. Many FAI packages fail audits because notes and specifications in the title block were overlooked during characteristic identification.
For complex machined parts, balloon drawings can easily exceed 100 characteristics. This is normal. The investment in thorough ballooning at the first article stage prevents measurement ambiguity during production inspection and makes re-inspection after changes significantly faster. At Nimble’s certified partner network, CMM inspection data is provided with FAI packages — actual point measurements tied directly to ballooned characteristics, not manual caliper spot-checks.
Material and Process Certifications in an FAI Package
Raw material certifications must meet the drawing callout exactly. If the drawing specifies AMS 2750 pyrometry, the heat treat supplier must provide a cert referencing that specification at the correct class and type — not a generic statement of compliance. If the drawing calls for aluminum 6061-T6 per AMS 2770, the material test report must show the actual chemistry and mechanical properties from the mill heat, not just a downstream distributor cert. Traceability to a specific heat or lot number is required.
Special processes — anodizing, plating, chemical conversion coating, heat treatment, NDT — each require their own conformance documentation. Nadcap accreditation of the process supplier is often a customer flowdown requirement for aerospace programs and must be verified and attached. Process specifications (AMS, MIL-SPEC, or customer-proprietary specs) must be listed on Form 2 and supported by supplier certs on Form 1. A missing Nadcap cert for a special process is a hard stop for many prime contractors.
Common FAI Failures and How to Avoid Them
The most frequent FAI deficiencies observed in aerospace supply chains include:
- Incomplete characteristic capture — drawing notes and specifications not ballooned or measured.
- Missing or non-conforming material certs — distributor certs substituted for mill certs, or certs referencing wrong specification revisions.
- Obsolete drawing revision on Form 2 — supplier working from a superseded rev without documented deviation or waiver.
- Pass/fail only on Form 3 — actual measured values not recorded.
- Unsigned or undated forms — forms without authorized signatures are not legally valid records under AS9100.
- Special process certs missing or expired — Nadcap certs lapse and must be current at time of FAI.
The most effective prevention is a formal FAI checklist reviewed during the pre-production kickoff, not at final inspection. Assign ownership of each form to a specific individual and set an internal review gate before submitting to the customer. Treat the FAI package as a deliverable with the same rigor as the hardware itself.
AS9102 in the Context of AS9100 and FAIR
The term FAIR (First Article Inspection Report) is used interchangeably with FAI package in most industry communication. The FAIR is the complete compiled package: all three forms, the balloon drawing, all material certs, all process certs, all NDT records, and any deviations or waivers. Some customers require the FAIR to be submitted in a specific format or through a quality management portal. Always confirm customer-specific requirements during contract review — they may supplement AS9102 with additional requirements.
For teams sourcing through a managed partner network like Nimble, AS9100 certification of the manufacturing partners is a baseline requirement. This means the FAI process is already embedded in the supplier’s QMS — you are not building it from scratch with each new source. Quotes from Nimble’s certified partner network include CMM inspection as standard, which directly supports Form 3 data quality and reduces the rework cycle on FAI package submissions.
Practical FAI Planning for Engineers and Procurement Teams
First, include FAI requirements explicitly in the purchase order. Reference AS9102B by name and revision, define which forms are required, specify the balloon drawing requirement, and list any customer-specific supplements or portal submission requirements. Ambiguity in purchase order terms is the root cause of most supplier disputes over FAI scope. Second, conduct a pre-production kickoff with the manufacturing supplier that covers the FAI plan — who is responsible for each form, what inspection equipment will be used, and what the submission timeline is relative to part delivery. Third, review FAI packages before hardware ships. An FAI package submitted alongside hardware leaves no time to address deficiencies without schedule impact.
For prototype and low-volume production runs where full AS9102 compliance may not be contractually required, it is still good engineering practice to document key characteristics and material traceability. This creates a baseline that makes future FAI requirements significantly easier to fulfill when the program scales to production volumes. The investment in documentation discipline early pays compounding returns as the program matures.
Get a quote from Nimble’s certified partner network.
Upload your drawings and get a detailed quote within 24 hours. Free DFM review included.
- What Is AS9102 and Why Does It Exist?
- When Is a First Article Inspection Required?
- The Three AS9102 Forms Explained
- Balloon Drawings and Characteristic Identification
- Material and Process Certifications in an FAI Package
- Common FAI Failures and How to Avoid Them
- AS9102 in the Context of AS9100 and FAIR
- Practical FAI Planning for Engineers and Procurement Teams